Caltrain completes three major milestones in electrification project

2 mins read

Californian commuter rail service Caltrain has announced the successful completion of three major milestones in its Caltrain Electrification Project, bringing the firm closer to its goal of more environmentally friendly passenger service in the fall of 2024.

The three milestones include: the installation of every pole for the overhead contact system (OCS), which provides power to the electric trains; the upgrade of the signal system that allows electric trains to operate along the Caltrain corridor; and successfully testing the new electric trains at maximum track speed of 79mph.

Caltrain and contractor Balfour Beatty have worked to install 2,569 pre-engineered poles and upgraded the existing signal system that will allow the electric trains to operate in an electrified corridor along the nearly 160-year-old right-of-way, which has continued to be an active railroad during this process.

The work in upgrading the existing signal system included upgrading every grade crossing on the electrified corridor. The steel poles were safely lifted and elevated into place and then mounted on a concrete foundation, a process that involved ongoing collaboration and hours of work around the clock to complete.

With the final OCS pole installed, crews can now hang the last of the wire, as well as finish the final work on the OCS that will provide power to the electric trains, which will be tested along the full corridor from San Francisco to San Jose later this year. 

Additionally, Caltrain and vehicle manufacturer Stadler, have successfully run tests using the OCS and the upgraded signal system with the new electric trains operating at maximum track speed to ensure that all the individual systems are working together as intended.

Cameras were placed atop the trains to ensure that the interface between the pantograph on the train and the OCS was fully integrated and operating as designed and constructed. The trains were first tested at walking speed and with each subsequent test the speed was increased until reaching the maximum authorized track speed of 79mph.  

“These three milestones are a big step forward for the Caltrain Electrification Project and we’re now even closer to completing this transformative project,” said Caltrain’s executive director Michelle Bouchard. 

The South San Francisco Traction Power Facility went live in August, making it possible to fully power the entire Caltrain electrified corridor once the testing and OCS is complete this fall. Trains are currently being tested on the southern end of the corridor and will be expanding to more parts of the system in the months to come. 

The 51-mile Caltrain Electrification Project will be the first 25KV OCS system on the west coast and will provide power to the new state-of-the-art-electric trains.

The electrification of the Caltrain system will deliver major benefits to the communities that it serves. Electrification will reduce Caltrain’s greenhouse gas emissions and eliminate the particulate matter caused by the aging diesel engines. Engine noise created by the trains will also be reduced.  

Service will become both more frequent and more comfortable as state-of-the-art electric trains replace the 30-year-old diesel fleet. The infrastructure that is being installed will also be compatible with future high-speed rail on the corridor.